HOLLESLEY BAY

HM PRISON

Sector

Blue Light

Client

Gasway Ltd

Project Manager

N/A

Architect

N/A

Value

£180K

Form of Contract

JCT 2011

Completion Date

February 2018

Duration

8 Weeks

Location

One of our existing clients required our expertise on this complex project for the renewal of underground heating infrastructure (communal heating). Due to the logistics of the project  works had to carried out in a live environment.

Within the ground, a 'Hi-line' preinsulated steel pipe was used with Viega Megapress XL jointing system was utilised.

The works completed by Redstar included all builders work associated (trenching and making good on completion). The project completed on time and to budget. 